05/08/25
​
Alright Alright Alright!
​
The concrete is drying and needs till roughly the 28th to cure properly so the team can come in and grind the floor to a nice polish before adding the clear coat.
​
In the meantime, the electrician has his deposit and will start work on the electric.
​
It's MOVING!!!! I'm so pumped right now.

04/27/25
​
The grease interceptor is in!!!
Expecting them to fill it in and finish it up this coming week.
​
We also need to pour cement in the shop this week as well as start the pony wall so we can run water lines and power.
​
We'll still need to grind and polish the floors at some point in there too.

NOW HIRING
Looking to hire a couple of baristas for multiple shifts, 7 days a week.
​​
04/20/2025
​​
---
​
Please contact john@whiterabbitcoffee.com
​
​

Mock-Up :
Signage for 11187 N Sheridan Blvd. #9
​
04/04/2025
​​
---
​
What.....you still don't have permits??
That's right. Revisions!!! Trying NOT to add a second bathroom. To do that means splitting hairs and praying the inspector ok's this. C'mon universe......throw me a bone here!!
​
​